New Croesyceiliog School - Latest News

June 2019

Internal works are progressing well in both the main building and sports building with mechanical and electrical (M&E) installation continuing on all floors including the installation of the fire sprinkler system and lifts.

Joinery works are well underway with fixed furniture being installed mainly in the science labs and ICT suites. Decorating continues, flooring and ceilings are being fitted throughout both buildings.

Externally we have seen construction of the car parks from the new Turnpike Road entrance with tarmac base course applied here and also around the Sports Building. Other landscaping works continue throughout the site with construction of retaining walls, block paving pathways and steps. Fencing to the perimeter of the site has also commenced.

Works to the bottom playing fields is nearing completion following the drainage works that have taken place over the last 12 months.

April/May 2019

Brickwork and rain screen cladding to all elevations is now complete with parapet cappings recently finished. Internal works are progressing at some pace with Mechanical & Electrical (M&E) installation continuing on all floors, joinery works are also well underway with fixed furniture being installed in some classrooms and laboratories. Decorating continues throughout both buildings and flooring is being laid. Installation of suspended ceiling grids is also underway.

The Sports Building continues with 1st fix of M&E, 2nd fix partitions and plastering.

Externally we have seen construction of the new car parks from the new Turnpike Road entrance and installation of fire hydrant & sprinkler tanks adjacent to the new Sports Building.

Landscaping works continue between the Main Building and the Sports Building with construction of retaining walls, pathways and steps. Works to the bottom fields is nearing completion.

In the next period internal works will continue with the installation of the fixed furniture throughout, 2nd & final fix M&E, final decorations, flooring & suspended ceilings.

January 2019

The Main Building to the new school is now substantially water tight with the roof complete, external facade framing and the majority of the windows have been now installed. Rain screen cladding to the new courtyard area has commenced.

The external brickwork is well underway which includes the working scaffold which is be erected as the brickwork progresses. The internal partitions for the room areas and the 1st fix M&E (Mechanical & Electrical) is well underway on all floors.

The Sports Hall external facade is substantially complete with a water tight milestone set for the middle of February 2019. The ground floor blockwork to the toilet areas has been completed.

External works are progressing. December saw the new Turnpike Roundabout entrance established which the contractor will start to utilise in February 2019 as the main entrance for site deliveries.

The next few months will see the completion of the external facades to both buildings and the continuation of 1st & 2nd fix partitions with the M&E elements continuing throughout construction.

Hard landscaping to the new car parking will also commence now that that the new entrance at Turnpike roundabout has been formed.

November 2018

Works on the new school have continued with considerable progress being made since the last update. Weatherboarding and insulation is almost complete to all elevations. Windows and frames are also being installed with brick tie channels being fitted in readiness for brickwork to commence to the external elevations of the main building.

The roof to the main building is complete with a system for safe access to the roof also installed. The sports building roof is approximately 90% complete.

The sports building blockwork has commenced along with the facing brickwork.

Within the main building, fire treatment to the 1st floor steel work is complete, timber soleplates are being fitted on the 1st and 2nd floors which will form the room partitions in readiness for the floor screed. Blockwork to the plant room and lift shaft is also underway.

External works are progressing with most of drainage works now finished. Some service diversions at the Turnpike Road roundabout were required plus the delivery of a new gas kiosk is awaited which will allow works to progress on the new school entrance and car parks.

Summary of works over the next month:

  • Completion of weatherboarding, insulation and brick tie channels on both buildings
  • Completion of windows to main building and commencing sports building windows
  • Continue brick and blockwork to both buildings
  • Continue fitting sole plates and commence partitions
  • Complete drainage works
  • Install new gas kiosk and changeover gas main
  • Complete cut/fill from Turnpike Road and carry out highways works to open Turnpike Road access road
  • Cladding to sports building
  • Tarmac to river footpath

July 2018

Work is well underway on the new buildings, Kier have their own secure offices and welfare units for staff with separate parking for construction staff. Temporary car parking and fire evacuation have been provided for the school which has allowed the contractor to complete preparatory works for the new buildings.  Kier as a ‘Considerate Constructor’ have long established procedures in place to ensure the site is safe and secure for all staff and pupils and constantly monitor operations on site to ensure these procedures are adhered to.

In the last month foundations have been completed with much of the steel frame for the new buildings erected, this is now clearly visible from Woodland & Turnpike Roads. During the period that the steelwork was being erected and to mark this key milestone in construction, Torfaen recently invited Kirsty Williams the Welsh Government Education Minister to site, along with representatives from Torfaen County Borough Council, Kier, Croesyceiliog School as well as other key stakeholders.

As well as much of the steel frame being completed, handrails, netting and metal decking is currently being fitted in preparation for the concrete pours which will form the floor slabs on each level, precast stairs to the main building have also been installed.

The haul road between the two new buildings is almost finished with a permanent refuelling area to be installed shortly. Drainage works to the western playing fields have also commenced and should be completed over the summer vacation.

In addition to the main construction works, we are pleased that Kier play a major part in ensuring there is involvement with the school pupils and local community in activities relating to the project. Pupil Ambassadors have been appointed who will visit site on a regular basis to view progress and will be able report back to their respective year groups both verbally and through social media, in fact their first visit took place on 9th July. Such engagement is also beneficial to pupils who may wish to consider a career in the construction industry.

See below for some of the activities that have taken place together with ideas for further engagement with the school. Kier also provide a regular newsletter for nearby residents to keep them up to date with construction progress.

Kier Community Activities

The next significant developments on site will include:

  • Works will continue on the drainage to the playing fields,
  • Formation of floor slabs to 1st & 2nd floors of the main building
  • Installation of internal drainage to main building once the 1st floor slab is poured.
  • Formation of new entrance road off Turnpike Road roundabout.
  • Install new gas kiosk.