New Croesyceiliog School - Latest News

November 2018

Works on the new school have continued with considerable progress being made since the last update. Weatherboarding and insulation is almost complete to all elevations. Windows and frames are also being installed with brick tie channels being fitted in readiness for brickwork to commence to the external elevations of the main building.

The roof to the main building is complete with a system for safe access to the roof also installed. The sports building roof is approximately 90% complete.

The sports building blockwork has commenced along with the facing brickwork.

Within the main building, fire treatment to the 1st floor steel work is complete, timber soleplates are being fitted on the 1st and 2nd floors which will form the room partitions in readiness for the floor screed. Blockwork to the plant room and lift shaft is also underway.

External works are progressing with most of drainage works now finished. Some service diversions at the Turnpike Road roundabout were required plus the delivery of a new gas kiosk is awaited which will allow works to progress on the new school entrance and car parks.

Summary of works over the next month:

  • Completion of weatherboarding, insulation and brick tie channels on both buildings
  • Completion of windows to main building and commencing sports building windows
  • Continue brick and blockwork to both buildings
  • Continue fitting sole plates and commence partitions
  • Complete drainage works
  • Install new gas kiosk and changeover gas main
  • Complete cut/fill from Turnpike Road and carry out highways works to open Turnpike Road access road
  • Cladding to sports building
  • Tarmac to river footpath

July 2018

Work is well underway on the new buildings, Kier have their own secure offices and welfare units for staff with separate parking for construction staff. Temporary car parking and fire evacuation have been provided for the school which has allowed the contractor to complete preparatory works for the new buildings.  Kier as a ‘Considerate Constructor’ have long established procedures in place to ensure the site is safe and secure for all staff and pupils and constantly monitor operations on site to ensure these procedures are adhered to.

In the last month foundations have been completed with much of the steel frame for the new buildings erected, this is now clearly visible from Woodland & Turnpike Roads. During the period that the steelwork was being erected and to mark this key milestone in construction, Torfaen recently invited Kirsty Williams the Welsh Government Education Minister to site, along with representatives from Torfaen County Borough Council, Kier, Croesyceiliog School as well as other key stakeholders.

As well as much of the steel frame being completed, handrails, netting and metal decking is currently being fitted in preparation for the concrete pours which will form the floor slabs on each level, precast stairs to the main building have also been installed.

The haul road between the two new buildings is almost finished with a permanent refuelling area to be installed shortly. Drainage works to the western playing fields have also commenced and should be completed over the summer vacation.

In addition to the main construction works, we are pleased that Kier play a major part in ensuring there is involvement with the school pupils and local community in activities relating to the project. Pupil Ambassadors have been appointed who will visit site on a regular basis to view progress and will be able report back to their respective year groups both verbally and through social media, in fact their first visit took place on 9th July. Such engagement is also beneficial to pupils who may wish to consider a career in the construction industry.

See below for some of the activities that have taken place together with ideas for further engagement with the school. Kier also provide a regular newsletter for nearby residents to keep them up to date with construction progress.

Kier Community Activities

The next significant developments on site will include:

  • Works will continue on the drainage to the playing fields,
  • Formation of floor slabs to 1st & 2nd floors of the main building
  • Installation of internal drainage to main building once the 1st floor slab is poured.
  • Formation of new entrance road off Turnpike Road roundabout.
  • Install new gas kiosk.
Last Modified: 05/12/2018